| INTRODUCTION | HISTORY | PROFESSIONAL STAFF | LAND SURVEYING | MUNICIPAL PROJECTS | SITE DEVELOPMENT | SLIP REMEDIATION | WATER PROJECTS | SEWER PROJECTS | BENEDUM AIRPORT | REFERENCES |
BENEDUM AIRPORT
CLICK
HERE FOR PICTURES
|
FEDERAL AVIATION
ADMINISTRATION •
Replacement of Runway & Taxiway Cables & Lights, |
1994-95 |
CONSTRUCTION $793,000 |
|
Benedum Airport now hosts the West Virginia Air Center (WVAC) facility, a project which began in 1989 and was completed in 1991. Also known as Phase I of the Mid-Atlantic Aerospace Complex, this multi-million dollar project resulted in major changes at the airport. Hornor Brothers Engineers was responsible for this work, which included the decommissioning of crosswind runway 13/31 and the following separate contracts (all under construction at the same time): |
|
ECONOMIC DEVELOPMENT
ADMINISTRATION, |
|
•
Construction of Lower Parking Area to Accomodate 500 Vehicles |
1990-91 |
CONSTRUCTION $487,900 |
|
PHASE I |
YEAR 1990-91 |
TOTAL COST $3,651,000 |
|
BENEDUM AIRPORT RUNWAY EXTENSION PROJECT: CLICK HERE FOR PICTURE Beginning in 1993, the Benedum Airport Authority embarked on a large and ambitious project to extend its main runway and parallel taxiway 1,800 feet to the north, plus another 1,000 feet of safety area. A 350 foot safety area was planned for addition to the south end. Hornor Brothers Engineers was hired to perform the engineering design services for this project. Major design components include a 10,000,000 cubic yard excavation and embankment; a 2,400 foot long, 72-inch structural steel culvert; runway and taxiway pavement and lighting; repaving the existing runway; fencing; utility line relocations; storm drainage system; and a new instrument landing system. The design and project documents were completed in 1995. Funding for the project was also finalized in 1995. Construction began in the Fall of 1996 and was completed in November 1999. Hornor Brothers was also chosen to provide all engineering services during the construction phase. The main runway has been extended from 5,200 feet to 7,000 feet. In addition to enabling larger planes to land and presently based aircraft to take off with full fuel loads and full payloads, this project has created a 45 acre level area near the runway which will be available for industrial and commercial use in conjunction with Benedum Airport and the existing Benedum Industrial Park. Year Total Cost Runway Extension Project 1996-1999 $31,500,000 |
|
ACCESS HIGHWAY: CLICK HERE FOR PICTURE The Benedum Airport Authority has hired Hornor Brothers Engineers to provide engineering design, inspection and construction management services for the construction of a 4,400 foot long (0.833 miles) access highway. The road intersects Route 73 (now 131) north of Bridgeport and runs in a southeasterly direction around the north end of the extended runway to the new industrial area created by the runway excavation near the Robert C. Byrd National Aerospace Education Center of Fairmont State College. This section of highway is known as Route 279, North Bridgeport Bypass. This project is unique in that most of the grading was performed by West Virginia Army National Guard units. The Guard began work on this project during the summer of 1994 and continued in a like manner thereafter through the 1999 summer. The West Virginia Division of Highways completed the paving during the year 2000. Based on conventional pricing, the access highway is a $2,100,000 project. Hornor Brothers has designed this road so that its alignment permited future extensions to both Route 50 to the east and and I-79 to the west, thus creating a highway which will be a complete northeast bypass of the City of Bridgeport. ARMY NATIONAL GUARD: CLICK HERE FOR PICTURE The West Virginia Army National Guard (ARNG) hired Hornor Brothers Engineers to provide all phases of engineering design and inspection for the construction of the Eastern ARNG Aviation Training Site Fixed Wing Detachment at Benedum Airport. This facility consisted of a 37,200 sq. ft. training facility hangar with classroom/administrative and aircraft maintenance space, flexible and rigid paving for aircraft parking, new taxiway access to the main runway, new taxiway access to the existing Tee Hangars, all supporting utilities, drainage structures, and new access highway from U.S. Route 50. Construction of the $7,000,000 project was completed in October, 1996 and is fully operational. |